Box 10
Contains 66 Results:
Highlights of the Consultants' Report on the Master Plan, press briefing, 1980 November 6
The consultants, E.D. Rosenfeld Associates Inc. and Baskervill & Son, recommend rebuilding the Medical Center on the Blue Ridge Hospital site.
Memorandum from Jules I. Levine to W. H. Muller;, 1981 April 24
Medical Center and University Planning: Observations and Recommendations. Levine is concerned about the excessive workload placed upon the Department of Physical Plant and the Health Affairs Office due to the large number of minor and major renovations which are all expected to be created in a time frame that is not possible given the various entities involved.
Executive Summary from Master Plan Update, 1981;, 1981, November 19
Prepared by Maurice W. Perreault and Associates, Inc.
Commonwealth of Virginia Capital Ourlay Request, Biennium 1984-86;, 1982 December 7
Relates to the Replacement Hospital and site preparation; total cost of the project is estimated to be $128,166,000.
Inside UVA: "Replacement hospital planners chosen";, 1983 January 1
The Cavalier Daily: "Mounting unpaid bills threaten hospital's financial well-being";, 1983 January 21
Almost $8.5 million in bad debts and free service were incurred from August to November 1982.
The Cavalier Daily: "Hereford will try to recoup state funds";, 1983 January 24
Gov. Robb proposed $55 millsion in state budget cuts to higher education.
The Daily Progress: "UVa's Frank Hereford: A Personal Perspective";, 1983 February 27
Interview with Hereford